Approval of appointment for works at Pleasley Vale

Decision status: Recommendations Approved (subject to call-in)

Is Key decision?: Yes

Is subject to call in?: Yes

Decision:

RESOLVED that 1) £153,900 + £15,000 (10% project contingency) of funding from the Transformation Reserve be allocated for the survey, design, technical documentation, technical supervision, and Principal Designer services for the high and medium priority recommended works to the culverts and associated infrastructure at Pleasley Vale,

 

2) the appointment of A2 Maritime to undertake the works as set out in the report, be approved,

 

3) £10,000 of funding from the Transformation Reserve be allocated for P&D Environmental to accompany A2 Maritime, as a requirement when undertaking inspections within the culverts under the confined spaces regulations,

 

4) a further report be brought back to Executive detailing the scope of services for the repairs and works to be carried out.

 

Publication date: 15/04/2026

Date of decision: 13/04/2026

Decided at meeting: 13/04/2026 - Executive

Date comes into force if not called in: 23/04/2026

Call-in deadline date: 22/04/2026

Current call-in Count: 0