Decision:

RESOLVED – That –

 

(1)       The Framework contract be awarded to Alfred Bagnall and Sons Ltd, Whittle Programmed Maintenance Ltd and Devlin Decorators Ltd for the provision of the Minor Painting Works Service for Bolsover District Council Housing Department.

 

(2)       The contract be awarded initially for a two years with the possibility of two additional periods each of one year.

 

(3)       The Assistant Director of Development be granted delegated authority, in consultation with the Housing Stock Group and the relevant Portfolio Holder, to extend the contract for the maximum of two additional periods each of one year. Extensions to be conditional upon the satisfactory performance of the contractor. 

Minutes:

Executive considered a report of the Portfolio Holder – Housing which sought approval to establish a framework of three Painting Contractors to provide a Minor Painting Works Service for Bolsover District Council Housing Department as and when required. This contract was to be available to all Council sections to utilise if required.

 

Moved by Councillor Sandra Peake and seconded by Councillor Mary Dooley

RESOLVED – That –

 

(1)       The Framework contract be awarded to Alfred Bagnall and Sons Ltd, Whittle Programmed Maintenance Ltd and Devlin Decorators Ltd for the provision of the Minor Painting Works Service for Bolsover District Council Housing Department.

 

(2)       The contract be awarded initially for a two years with the possibility of two additional periods each of one year.

 

(3)       The Assistant Director of Development be granted delegated authority, in consultation with the Housing Stock Group and the relevant Portfolio Holder, to extend the contract for the maximum of two additional periods each of one year. Extensions to be conditional upon the satisfactory performance of the contractor. 

 

REASON FOR DECISION:

Following a procurement exercise, taking into account both cost and quality evaluation criteria, the three contractors were invited to form the framework.

 