Issue - decisions

Mine Water Energy Demonstrator and HNDU Feasibility Study

11/09/2024 - Mine Water Demonstrator and Heat Network Project

RESOLVED that 1) the acceptance of funding from the Heat Network Distribution Unit be noted,

 

2) the novation of the contract for the Mine Water Energy project from D2N2 to EMMCCA with the effect of accepting the £900,000 funding originally awarded by D2N2 be agreed,

 

3) the procurement of ENER-G Renewable Solution Ltd to construct and operate the demonstrator and small heat network in Creswell serving the Creswell Heritage and Wellbeing Centre in the first instance be approved,

 

4) Delegated authority be given to the Chief Executive Officer to make the decision to agree the contract price with ENER-G Renewable Solutions Ltd subject to this not exceeding £200,000