Issue details

To appoint a contractor to erect a heavy duty scaffold crash deck in mill 1, Pleasley Vale

Decision type: Key

Reason Key: Revenue Income or Expenditure of £75,000 or more;

Decision status: For Determination

Notice of proposed decision first published: 22/10/2025

This decision will be taken under urgency procedures.

Reason for urgency:
To erect a heavy-duty scaffold crash deck to safeguard against falling masonry and structural integrity of Block A (Mill 1) and allow other sections of the Mill to re-open and address Derbyshire Building Control safe requirements. Due to urgency of the works to meet safety requirements, a supplier is required so urgently so as to preclude tenders. This item is exempt from Scrutiny Call-In.

Decision due: 22 Oct 2025 by Chief Executive
Reason: Urgent

Delegated Decision Notice

Lead member: Portfolio Holder - Growth

Lead director: Chief Executive

Contact: Sally Lovell, Business Centres Manager Email: sally.lovell@bolsover.gov.uk.